Updates Regarding the Village’s 2022 Construction Projects

Zj

This update has been provided to you by our partners at Town and Country Engineering.

Terminal Drive Reconstruction (Contract A):

Cattell is the general contractor for this project.

A Public Information Meeting (PIM) for the project was held on June 1, 2022.

Watch the PIM via McFarland Cable

Installation of new storm sewer is expected to continue into the week of June 27, 2022. This work is generally progressing from north to south. Residents should expect full road closure at the storm sewer installation location.

Grading and excavation is expected to continue into the week of June 27, 2022.

Private utility relocations are ongoing.

Construction completion is projected for late August.

Overview map of the finished project corridor (PDF).

Hidden Farm Road Reconstruction (Contract B):

Wolf Paving is the general contractor for this project.

Road excavation and grading is planned for the week of June 27, 2022.

Construction completion is projected for late June.

Overview map of the finished project corridor (PDF).

Storck Road Pavement Replacement (Contract B):

Wolf Paving is the general contractor for this project.

Asphalt pulverizing was completed on June 20, 2022.

Road grading will continue into the week of June 27, 2022.

Construction completion is projected for early July.

View a map of this project area (PDF).

Card Avenue Water Main Replacement (Contract B):

Wolf Paving is the general contractor for this project.

The project has an anticipated start date of July 5, 2022

Construction completion is projected for the first week in September.

View a map of the project limits: 2022 Water Main Replacements (PDF).

Lake Edge/Bremer Road Water Main Replacement (Contract B):

Wolf Paving is the general contractor for this project.

The project has an anticipated start date of July 5, 2022

Construction completion is projected for the first week in September.

View a map of the project limits: 2022 Water Main Replacements (PDF).

Terminal Drive Rail Bridge and Osborn Pond Storm Sewer Repairs (Contract C):

R&T Voegeli Excavating is the general contractor for this project.

The project has an anticipated start date of mid-July or early August.

View a map of these project areas (PDF).

Additionally, the latest on Exchange Street, which is planned for 2024 construction is:

Exchange Street:

The project extents are from Farwell Drive to Sleepy Hollow Road.

A full street reconstruction is planned with the addition of bike lanes, new sidewalk on the west side, new storm sewer, water main replacement, and sanitary sewer improvements.

A third Public Information Meeting (PIM) is planned for October or November of this year.

The latest PIM can be viewed on demand via McFarland Cable.

Additional information, documents, and images can be found on the Exchange Street Reconstruction - Capital Projects page.

Source: https://www.mcfarland.wi.us/CivicAlerts.aspx?AID=267

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS