Updates Regarding the Village’s 2022 Construction Projects: August 26th

This update has been provided to you by our partners at Town and Country Engineering.

Terminal Drive Reconstruction (Contract A):

Cattell is the general contractor for this project.

A Public Information Meeting (PIM) for the project was held on June 1, 2022.

Watch the PIM via McFarland Cable

Private utility relocations are ongoing.

Curb and gutter installation is complete.

Sidewalk installation is complete.

Path construction is planned for the week of August 29th.

Construction completion is projected for mid-September.

Overview map of the finished project corridor (PDF).

Hidden Farm Road Reconstruction (Contract B):

Wolf Paving is the general contractor for this project.

This road is fully paved and open to traffic.

Overview map of the finished project corridor (PDF).

Storck Road Pavement Replacement (Contract B):

Wolf Paving is the general contractor for this project.

Some landscaping and shouldering work remain to be completed.

View a map of this project area (PDF).

Card Avenue Water Main Replacement (Contract B):

Wolf Paving is the general contractor for this project.

Water service lateral installations on Card Avenue and Bellevue Court are expected the week of August 29th.

Construction completion is projected for mid-September.

View a map of the project limits: 2022 Water Main Replacements (PDF).

Lake Edge/Bremer Road Water Main Replacement (Contract B):

  • Wolf Paving is the general contractor for this project.
  • Paving and initial restoration on this project have been completed.
  • View a map of the project limits: 2022 Water Main Replacements (PDF).
Terminal Drive Rail Bridge and Osborn Pond Storm Sewer Repairs (Contract C):

R&T Voegeli Excavating is the general contractor for this project.

Work near Osborn Pond is expected to be completed early during the week of August 29th.

Work under the Terminal Drive rail bridge is expected to be completed in coordination with the railroad in late September.

View a map of these project areas (PDF).

Additionally, the latest on Exchange Street, which is planned for 2024 construction is:

Exchange Street:

The project extents are from Farwell Drive to Sleepy Hollow Road.

A full street reconstruction is planned with the addition of bike lanes, new sidewalk on the west side, new storm sewer, water main replacement, and sanitary sewer improvements.

A third Public Information Meeting (PIM) is planned for October or November of this year.

The latest PIM can be viewed on demand via McFarland Cable.

Additional information, documents, and images can be found on the Exchange Street Reconstruction - Capital Projects page.

This update has been provided to you by our partners at Town and Country Engineering.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS